Delivery Forecast guide

Install Delivery Forecast, see when every release and epic is likely to be done, plan around holidays and days off, and add it to your dashboards.

Updated Nov 12, 2026

Before you start

You need:

  • A Jira Cloud site, and admin rights on it to install apps.
  • A Jira Software project with some finished work. The forecast learns from what your team has finished in recent weeks or sprints.
  • Project admin rights to change the Team calendar and Settings. Anyone who can browse the project can see the forecasts.

Delivery Forecast is a paid app with a free trial on the Atlassian Marketplace. During the trial and while subscribed, everything is included. Without an active trial or subscription the app explains that a Jira admin can subscribe from Apps, ⋯, Manage apps in the Jira sidebar, or from Connected apps in Atlassian Administration.

1. Install the app

  1. Open the Delivery Forecast listing on the Atlassian Marketplace and select Try it free.
  2. Choose the Jira site to install it on.
  3. Review the permissions and confirm.

You can also install it from inside Jira: open Settings (the gear icon), go to Apps and search for "Delivery Forecast".

Installing Delivery Forecast from the Apps screen in JiraInstalling Delivery Forecast from the Apps screen in Jira

The app only reads from Jira and never changes your issues. It keeps a short history of finished work (issue IDs, finish dates and story points, no issue content), your team calendar and your project settings in Atlassian's Forge storage. No data leaves Atlassian.

2. Open Delivery Forecast

Go to your project and choose Delivery Forecast in the project navigation. If your project has a lot of tabs, look under More.

The Delivery Forecast tab in the project navigationThe Delivery Forecast tab in the project navigation

No finished work yet? Select Show sample data to see how the app works with a made-up team. Nothing is stored or sent.

3. Check every release and epic

The Overview tab shows every open release and epic, riskiest first: how much is done, the work left, the likely and safe dates, the due date and a red, amber or green chance of meeting it. Select a row to open its finish date.

Every open release and epic with its chance of meeting the due dateEvery open release and epic with its chance of meeting the due date

4. Read the finish date

The Finish date tab gives three dates: Likely (half of the outcomes finish by then), Safe to promise (85 in 100) and Very safe (95 in 100). They come from 10,000 replays of your team's recent weeks or sprints. You can forecast a release, an epic, a board, the whole project, a favourite filter or your own JQL, in issues or story points, and use Pace from to forecast at another board's pace.

With a due date you also see the chance of hitting it and how many days late the likely and safe dates are. Change the work left, the capacity or when work starts to try a what-if. By a date answers the opposite question: how much you will finish by a date you pick.

Likely, Safe to promise and Very safe dates with the probability curveLikely, Safe to promise and Very safe dates with the probability curve

5. Plan your team (optional)

Open the Team tab to tell the forecast about smaller weeks. Plan by team size, or by person: each person's time on the team and their days off, in a calendar (select a week, then pick the days) or a list. Add team holidays as well. The weekly totals and every forecast update straight away.

Only project admins can change the calendar. By default, only project admins see who is away; everyone else sees the team totals per week, which give the same forecast. An admin can change this in Settings.

The team calendar with time on the team, days off and team holidaysThe team calendar with time on the team, days off and team holidays

6. Add it where you look

Add the Delivery Forecast widget to a dashboard (new and classic dashboards), then edit it to choose a project and show either the Overview of releases and epics or one forecast.

Adding the Delivery Forecast widget to a dashboardAdding the Delivery Forecast widget to a dashboard

Open any epic to see the Delivery Forecast section in the right-hand sidebar, with the work left, the likely and safe dates and the chance of meeting the epic's due date. It does not appear on other issue types.

The Delivery Forecast section in the sidebar of an epicThe Delivery Forecast section in the sidebar of an epic

Troubleshooting

Every screen says the app needs an active subscription. The trial has ended or was never started. A Jira admin can start the trial or subscribe from Apps, ⋯, Manage apps in the Jira sidebar, or from Connected apps in Atlassian Administration.

The forecast says there is no finished work. The forecast needs work your team has finished recently. Pick another board or the whole project, or select See an example with sample data to see how it works.

The forecast shows a note about the history. When the history is short, thin or very uneven, the app says so in plain words. The dates are still shown, but treat them with more care.

I cannot change the Team tab or Settings. Only project admins can. Ask one to make the change or to grant you the permission.

My forecast counts fewer issues than a colleague's. Every forecast only uses issues you can see. Issues in projects you cannot browse, or with a security level you cannot see, are left out.

Uninstalling

Remove the app from Connected apps in Atlassian Administration (admin.atlassian.com). Your team calendars, settings and the finished-work history are deleted with the app, under Atlassian's data retention policy for Forge storage.